Work to start on new multi-purpose building in Pitäjänmäki

The project to both renovate and extend the existing comprehensive school building in Pitäjänmäki is about to start. The operations will move to temporary premises by summer 2026 at the latest, when the demolition of the current extension will begin.
Valkoisia taloja, sininen taivas ja sisäpiha.
An illustration of the Pitäjänmäki multi-purpose building after renovation and expansion. Photo: Renell Käppi Arkkitehdit Oy

In the summer, a project to renovate the main building of Pitäjänmäki Comprehensive School at Viinenkuja 6 and build two new buildings to replace the existing extension will start in Pitäjänmäki. 
The buildings will have around 50% more space than at present, and the number of pupils will increase accordingly. The multi-purpose building will house the 680-pupil Pitäjänmäki Comprehensive School and Daycare Taneli with space for 224 children. The Pitäjänmäki Library and Youth Centre will also continue their operations in the premises.
Special attention will be paid to hearing accessibility in the design and implementation of the buildings.

Operations to move to temporary premises by June at the latest

The premises currently house Pitäjänmäki Comprehensive School, Youth Centre, the after-school activities of Playground Nuoli and Pitäjänmäki Library. In addition to this, Daycare Mestari operates in the pavilion building on the site. All activities will move to temporary premises in June at the latest, with the library and youth centre likely to move already in the spring.
The temporary premises are located at the following addresses, and users will be provided with more information on them closer to the time of the move:

  • Comprehensive school and youth centre: Hiomotie 5
  • School physical education classes: Kutomokuja 4
  • After-school activities: new Playground Nuoli (Nuolitie 5) to be completed in autumn 2026
  • Library: Ristikko shopping centre (Ajomiehentie 1)
  • Groups from Daycare Mestari will be placed in other daycare centres in the area. 
     

Renovated premises ready for use in autumn 2029

Demolition work will begin in the summer, with the actual renovation and new construction starting in autumn 2026. The development phase of the project, during which the technical solutions and cost levels will be specified, has started. Consti Korjausrakentaminen Oy has been selected as the contractor for the development phase.
Project timetable:

  • March–autumn 2026: development phase
  • May–June 2026: relocation of activities to temporary premises
  • summer 2026: demolition of the old extension and pavilion
  • autumn 2026–March 2029: renovation and construction of additional facilities 
  • autumn 2029: start of operations in the new premises
     