Bridge over Itäväylä to be closed for repairs in Kulosaari

The renovation of Hopeasalmentie bridge will start in early February and last until October 2026. The bridge will be closed to all traffic when the work starts. At the bridge, the lanes of Itäväylä will be closed in stages.
A map of the work area.
The Hopeasalmentie bridge will be closed to all traffic when the work starts.

The Hopeasalmentie bridge crosses Itäväylä between Kulosaarentie and Kulosaaren puistotie. The bridge deck is in poor condition and the waterproofing has reached the end of its life. It is cost-effective to renovate the whole bridge at once in connection with replacing the deck and waterproofing.

The project involves repairing the bridge and the metro tunnel at its northern end, renovating the district heating line and replacing the street surface structures near the junctions at both ends of the bridge.

The bridge deck will be demolished in March by sawing and drilling, which will generate noise in the vicinity.

While the Hopeasalmentie bridge is closed, pedestrians and cyclists will be diverted to cross Itäväylä via the Adjutantinpolku underpass. Bus line 16 will run via Kulosaari during the works. The work will not affect metro services. For more information on changes to public transport services, please visit  HSL’s website(Link leads to external service) .

The contractor is Kreate Oy.